Webwerks India Pvt Ltd (An Iron Mountain JV)
ESR Data Centres Case Study

Webwerks India Pvt Ltd (An Iron Mountain JV)
ESR Data Centres.
Location :Rabale (In Progress)

Scheme: Double Bus Configuration.
Capacity : Phase 1: 120 MVA
Voltage Level/Type: 220Kv and 132Kv

Value Proposition

  • Concept to commissioning including design build of substation till power to Data centre building.
  • Phase-1 on 220Kv upto 150 MVA.
  • Final Designs at LOD 500 along with clash detection for optimised constructability.
  • G+1 structure to optimise footprint of GIS.
  • Overhead 220KV and 132Kv Incoming lines with 2500 Sqmm Cable till the GIS Substation.

Scope: Power Sanction,Supply, Installation, Testing and Commissioning, Power Release, Including Civil Works on Turnkey Basis.

Voltage Level: 220/22Kv Substation
In progress: 18 Months